oa Civil Engineering = Siviele Ingenieurswese - 6 - Gautrain Project South Africa : Southern Viaduct Section
Superstructure design and construction : construction and project management

 

Abstract

The successful design, manufacture and construction of the viaduct superstructure with its precast segmental format was the key to the timeous completion of these sometimes vast structures. Reaching the final solution required extensive planning and interaction between the design subconsultants (VelaVKE), the Bombela Joint Venture supervisory team, the casting yard where the segments were to be manufactured, and VET , the viaduct erection specialists.