1887

n Civil Engineering = Siviele Ingenieurswese - Esor Pipelines on track with Western and Northern Aqueducts in KZN : on the cover

USD

 

Abstract

Esor Pipelines, a division of Esor Construction, has completed 34% of its 36 month contract on the Western Aqueduct Phase 2 for client eThekwini Municipality in Durban, KwaZulu-Natal, reports Contracts Manager Stephen Cahi. The scope of work is the construction of 17 km of DN 1 400 mm and 8 km of DN 1 000 mm continuously welded pipeline.

Loading

Article metrics loading...

/content/civeng/23/2/EJC167238
2015-03-01
2016-12-02
This is a required field
Please enter a valid email address
Approval was a Success
Invalid data
An Error Occurred
Approval was partially successful, following selected items could not be processed due to error