oa Civil Engineer in South Africa - Design and construction of the permanent way for the Sishen-Saldanha rail link

 

Abstract

The design parameters for the rail track for the Sishen-Saldanha railway line were established following studies of rail systems throughout the Western world. Change from the 1 065 mm gauge used in South Africa could not be justified and basic design philosophies developed by the South African Railways over the years, modified to suit the particular requirements anticipated, were adopted - with cognizance being taken of certain expected future technological developments.


With available construction time being severely limited, highly mechanized methods of platelaying were essential to achieve approximately 3 km / d progress over sustained periods. Severe logistic and human problems had to be overcome during this high-rate platelaying operation through remote Western Cape areas, extending over 861 km and including the construction of eight passing loops, a halfway station and two major marshalling yards.

Die ontwerpstandaarde vir die spoorbaan van die Sishen-Saldanha spoorlyn is opgestel nadat 'n studie van spoorstelsels dwarsdeur die Westerse wêreld gemaak is. 'n Afwyking van die 1 065 mm spoorwydte wat in Suid-Afrika gebruik word kon nie geregverdig word nie en die basiese ontwerpfilosofie wat oor die jare deur die Suid-Afrikaanse Spoorweë ontwikkel is, is aanvaar. Wysigings is egter in die finale ontwerp gemaak om by spesifieke vereistes aan te pas en om vir sekere verwagte toekomstige tegnologiese ontwikkelinge voorsiening te maak.


Met die beperkte konstruksietyd beskikbaar was hoogs gemeganiseerde metodes van spoorlegging noodsaaklik om die volgehoue vordering van ongeveer 3 km / d oor 'n lang tydperk te handhaaf. Ernstige logistieke en menslike probleme moes oorbrug word gedurende die tydperk van hoë tempospoorlegging oor 'n roete-afstand van 861 km deur afgeleë Wes-Kaaplandse gebiede. Die aanbou van agt verbygangslusse, 'n halfwegstasie en twee belangrike rangeerwerwe by die begin- en eindpunte is in die spoorstelsel ingesluit.

Loading

Article metrics loading...

/content/civeng1/21/1/EJC24755
1979-11-01
2016-12-04
This is a required field
Please enter a valid email address
Approval was a Success
Invalid data
An Error Occurred
Approval was partially successful, following selected items could not be processed due to error