The design of the dam was divided into three phases. Phase 1 was the basic design, in which detailed geotechnical investigations were con ducted, a dam type selection study was performed and the dam layout was optimised and finalised. Phase 2 comprised the tender and construction designs, and phase 3, construction supervision. The Braamhoek Consultants Joint Venture (BCJV) was successful in its bid for phase 1 and a contract was signed in May 2004.